Project Timeline

Design Schedule

  • Start - December 2005
  • Finish - September 2007

Construction Schedule

  • Start - October 2007
  • Finish - February 2009

Planning Meetings

Planning Group Samples Planning Discussion


Architectural Renderings

Schematic Designs
Floor Plans
Schematic Floor Plan

*Adobe Acrobat Reader is required to view PDF files.


Building Site Preparation


With the demolition of Gilbert and Thomson Halls (built in 1947) on Dickey Drive, construction for the new psychology building is set to begin in fall 2007.

The next step of the process calls for realigning North Oxford Road and Dickey Drive to create space for the building adjacent to Atwood Hall (chemistry).

Emory College

About the Project | Psychology at Emory | Planning, Design & Construction | People | Giving Opportunities
Emory College | Emory University

 

Copyright © Emory University
Last updated: September 26, 2008
Please direct questions or comments to college@emory.edu

Science Commons homepage Emory University